Semiconductor Modular Assembly
Semiconductor Modular Assembly
Project scope included pre-construction activities, engineering design-assist, and pipe rack module fabrication, assembly, and heavy transportation for over 500 Trestle Modules:
- 9,000 tons of structural steel
- 130,000 LF pipe (carbon, low purity & high purity stainless, plastics)
- 70,000 LF cable tray
- 18,000 pipe supports
- Heavy haul transport from Texas to Arizona (two day trip)
| Client | Confidential |
| Location | Chandler, Arizona |