Bradley Gas Plant

Enable Midtream Partners, LP


Client: Enable Midstream Partners, LP | Burns & McDonnell

Location: Bradley, OK

Scope: Construction services include the erection of structural steel, setting of modules, and installation of the mechanical equipment (including amine, demethanizer, dehydrators, and multiple skids) for a UOP Russell 200 MMSCFD cryogenic facility.

Equipment:

  • Demethanizers – Curtis Kelly
  • Dehydrators and Amine – Professional Projects
  • 165 pieces of overall equipment

Duration: 6 months