Enterprise Products RGB Unloading Project


Client: Enterprise Products Partners, L.P.

Location: Pasadena, Texas

Scope:  Partner of EPC team that designed and installed all facilities and infrastructure necessary to unload RGB product to client’s facility.  The project is a RGB unloading system at a facility in Pasadena, TX.  The project presented unique challenges as it involved the relocation of multiple pieces of equipment and over 1,000 LF of existing piping at the client’s facility in La Porte, TX.  The scope of work consisted of all piping (several miles routed through an existing rack), foundations, structural steel, equipment setting, grout, testing, electrical, instrumentation, and start up support.  The new dock unloading system was installed along the Houston Ship Channel, which allows barges filled with RGB product to be unloaded and transferred to existing pipeline facilities.

Duration: 7 Months

Contract:  Lump Sum

Enterprise PPT 1